Ludlow Construction is planning to commence construction operations on Newton Street, between the Route 202 intersection in the south and Kendrick Street in the north, on Thursday, July 28th. Specific items of work are listed below, per the contractor’s most recent schedule. The only work occurring in the permitted areas this year will be the clearing and grubbing.
Tree & plant protection fence, tree trimming, removal - August
Drainage – July to early September
Retaining walls (near Camden Street & across from the high school) – mid August to mid October
Herbicide/clearing & grubbing at dam locations – mid September
Curb, widening, wheelchair ramps – late September to early November
Underground electrical & signal foundations (Lyman St intersection & fire station) – mid September to early December